Home Page > Case Studies : Equipment Installation, Commissioning, Validation and Training
Equipment Installation, Commissioning, Validation and Training
We
were commissioned by a contract pharmaceutical manufacturer to increase
the throughput of a coating facility.
Project Scope:
Install a coating machine - a GLATT "Coater GC 1000" - from another
leading pharmaceutical manufacturers site. Perform associated commissioning,
validation and training activities.
Scope of Services:
-
Audit of the machine before moving
- Parameters and performance
- Risk assessments
- Cabling, HVAC balancing, SAT
- Qualification - from DQ to PQ
- Cycle development and optimisation
- Using knowledge from work at the previous site and qualification activities at the new site
- Product validation runs were also performed by the client's own operators
Commissioning and start up
Cleaning and product validation
Operator training
Results:
- 9 weeks from commissioning to production.
- Product validation performed without non conformity.
- Operators fully trained and able to produce validatable batches without supervision.