Equipment Installation, Commissioning, Validation and Training

Image of the coating machine - a GLATT Coater GC 1000We were commissioned by a contract pharmaceutical manufacturer to increase the throughput of a coating facility.

Project Scope:
Install a coating machine - a GLATT "Coater GC 1000" - from another leading pharmaceutical manufacturers site. Perform associated commissioning, validation and training activities.

Scope of Services:

    Audit of the machine before moving
  • Parameters and performance
  • Risk assessments

  • Commissioning and start up
  • Cabling, HVAC balancing, SAT
  • Qualification - from DQ to PQ
  • Cycle development and optimisation

  • Cleaning and product validation
    Operator training
  • Using knowledge from work at the previous site and qualification activities at the new site
  • Product validation runs were also performed by the client's own operators

Results:
  • 9 weeks from commissioning to production.
  • Product validation performed without non conformity.
  • Operators fully trained and able to produce validatable batches without supervision.