HAL Line Blockage Inspection and Clearance System
British Nuclear Group required that a system be produced to inspect, sample and clear a blockage that had occurred in a HAL Line on Sellafield site. Following integrated BNG and Assystem Limited team "brainstorming" sessions, Assystem carried out initial scheme design proposals, full detail design, manufacture, assembly, and test & development of the first system with the first system used on Site within 3 months of project initiation. The project further developed another 31 units, successfully deploying 14 on site. The remaining units were held at JoRDI for further development into a generic system and for possible future use on other site inspection requirements.
The system was required to remotely deploy a specially designed miniature camera & lighting inspection head, combined with a high pressure water jetting line down the 50 mm nominal bore HAL Line pipe to the blockage.

- Mechanical Design
- Electrical and Control Design
- Manufacturing engineering
- Project Management
Project Statistics:
- Maximum team size 21
- Project value £900k
- Duration 2 years
Achievements:
- Single team culture between BNG R&T, BNG Site personnel & Assystem staff.
- Highly productive and focussed team.
- Full involvement of all disciplines and functions from project initiation.
- Successful design of miniature integrated camera & lighting unit specifically designed for the task.
Secondary Benefits:
- The HAL Line inspection & clearance system to be developed for generic use on Sellafield site.
- Multiple and varied special to type inspection systems designed and manufactured for various Sellafield plant applications.